‧Product - Engineering service - Clean Room System
 
 
 

Our company has had years of experience in contacting with clean room project to date. With internal training and team integration, we have undertaken turnkey projects for building entire clean room and factory system at home and abroad. The supplied environment and facilities, and stable clean room environment can improve the good rate of product in order to comply with the production process. We can make the entire factory building integration for you.


Project of clean room system includes:

  • Interior finishing engineering of clean room: discussion of traffic route, flow and rules
  • Interior finishing engineering of clean room: discussion of traffic route, flow and rules
  • Electric engineering: discussion of lighting, equipment electricity of clean room and machine electricity integration
  • Fire engineering: discussion of FM and demand for domestic rules
  • Instrument control engineering: discussion of environment control precision and control point

In the process of constructing the clean room, in addition to taking particular consideration of the construction quality of each system, the integration of each constructing project and the control of cleaning stage are especially important. It mainly includes:

  • Space planning within clean room
  • Pipeline planning within clean room
  • Cleaning schedule planning within clean room
  • Discussion of entire factory system and construction

Test after finishing the clean room is an important work to determine if the project in accordance with the original design specifications. Mainly test items are:

  • Air flow velocity test
  • Filter leakage test
  • Air borne particle count test
  • Room pressurization test
  • Temperature / humidity test
  • Noise level test
  • Illumination test
  • Floor covering resistance test
  • Wall to ground resistance test

With regard to the test of clean room, the project will be adjusted according to requirements of standard.